Holtec and Ameren Complete Major Civil Construction at Callaway Paving the Way for the Inaugural Loading Campaign of HI-STORM UMAX in Late Summer
The arrival of spring in Missouri coincides with the completion of major civil work on the HI-STORM UMAX ISFSI at Ameren’s Callaway Nuclear Power Plant. The transformation from the support pad with the 48 Cavity Enclosure Containers (CECs) at the bottom of a 25 foot deep excavation in November of 2014, to the current state of completion with the ISFSI Pad, curbing and apron completed and 6 HI-STORM UMAX lids ready for installation is truly a credit to Ameren/Holtec teamwork. The heavy haul path from the Fuel Building to the ISFSI pad is also complete. (more…)