No. The ground load will remain substantially unchanged after the subterranean storage system is installed and placed in service with loaded multi- purpose canisters. This is because the mass of the earth removed to make the canister storage cavity approximates the combined mass of the constructed storage cavity and its stored multi-purpose canister. Therefore, long-term settlement of the site caused by a large increase in the load overburden is not possible.