Every plant owner has two years from the date that a reactor permanently ceases operations to submit its Post-Shutdown Decommissioning Activities Report (PSDAR) and site-specific Decommissioning Cost Estimate (DCE) to the U.S. Nuclear Regulatory Commission (NRC). The Palisades PSDAR and DCE were submitted to the NRC by Holtec as a supplement to the Palisades License Transfer Application. Those submittals will be formally docketed shortly after close of the Palisades transaction and license transfer from Entergy to Holtec.