What is the timeline to move the remaining spent fuel to the Independent Spent Fuel Storage Installation (ISFSI)?
The fuel assemblies in the spent fuel pool will be moved into dry cask storage on the ISFSI pad beginning in January 2021 and will be completed by November 2021.